Time left 1 A can do a certain work in the same time in which B and C together can do it. If A and B together could do it in 10 days and C alone in 50 days, then B alone could do it in: 15 days 20 days 25 days 30 days 2 A can do a piece of work in 4 hours; B and C together can do it in 3 hours, while A and C together can do it in 2 hours. How long will B alone take to do it? 8 hours 10 hours 12 hours 24 hours 3 If 6 men and 8 boys can do a piece of work in 10 days while 26 men and 48 boys can do the same in 2 days, the time taken by 15 men and 20 boys in doing the same type of work will be: 4 days 5 days 6 days 7 days 4 A alone can do a piece of work in 6 days and B alone in 8 days. A and B undertook to do it for Rs. 3200. With the help of C, they completed the work in 3 days. How much is to be paid to C? Rs. 375 Rs. 400 Rs. 600 Rs. 800 5 A is thrice as good as workman as B and therefore is able to finish a job in 60 days less than B. Working together, they can do it in 20 days 22 1/2 DAYS 25 days 30 days 6 A, B and C can do a piece of work in 20, 30 and 60 days respectively. In how many days can A do the work if he is assisted by B and C on every third day? 12 days 15 days 16 days 18 days 7 A can do a work in 15 days and B in 20 days. If they work on it together for 4 days, then the fraction of the work that is left is : 1/4 1/10 7/15 8/15 8 A can lay railway track between two given stations in 16 days and B can do the same job in 12 days. With help of C, they did the job in 4 days only. Then, C alone can do the job in: 9 1/5 DAYS 9 2/5 DAYS 9 3/5 DAYS 10